PRIOR HISTORY: [***1]
Appeal by defendant from
Bailey, Judge. Judgment entered 8 November 1978 in Superior Court, Wake
County.
DISPOSITION:
Affirmed.
CASE SUMMARY:
PROCEDURAL POSTURE: Defendant,
a successful bidder on a subcontract, appealed a decision by the Wake
County Superior Court (North Carolina), which held in favor of plaintiff,
a general contractor, and which directed a verdict in favor of the general
contractor on the general contractor's claim against the bidder under the
subcontract.
OVERVIEW: At issue was whether
the bidder was bound by its subcontract with the general contractor when
the general contractor asked the bidder to submit a starting time and
when, two months later, the general contractor gave the bidder notice to
perform. The court held that the bidder was obligated to perform under the
subcontract. The bidder had signed the subcontract and had agreed to
incorporate the conditions of the general contractor's contract with a
county and to commence work "when notified" by the general
contractor. The general contractor's request to the bidder to begin work
was made within the original time period plus the 334-day time extension
granted by the county. The bidder assumed the risk that the cost of the
work would go up before the job would be completed and the risk that the
time for performing the work would be extended. The court found that the
bidder could not later deny those self-assumed obligations even if the
course of events proved them to be harsh. Furthermore, the language
"for the duration of the job" was not so ambiguous so as to make
the subcontract unenforceable.
OUTCOME: The court affirmed
the trial court's ruling on the general contractor's motion for a directed
verdict on the general contractor's claim as well as the trial court's
ruling on the bidder's counterclaim.
SYLLABUS:
The plaintiff [***2] in this
civil damage action, T. A. Loving Company, is a general contractor on
contract with Durham County to build a hospital. The defendant, Oscar
Miller Contractor, Inc., subcontractor with the plaintiff to provide
asphalt paving and curb and gutter work for the hospital. The plaintiff
alleged that defendant refused to perform under its contract. The
defendant denied liability on the ground that the contract was terminated
by plaintiff's failure to request performance within a reasonable period
of time. Defendant also filed a counterclaim alleging that the plaintiff's
failure to request performance within a reasonable period of time was a
breach of contract.
The following evidence is
undisputed. On 2 June 1972 plaintiff entered into a contract with Durham
County (the "Owner") to build a nine-story hospital. The
contract consisted primarily of the "Agreement," the
"General Conditions" and "all Modifications issued
subsequent thereto." Paragraph 43 of the General Conditions, as
modified by the Supplemental General Conditions, contained a subsection on
delays and extensions of time which explicitly provided that upon the
occurrence of certain conditions, or when authorized by [***3] the Owner
or Architect, "the Contract Time shall be extended by Change Order
for such reasonable time as the Architect may determine."
It is also undisputed that on
14 June 1972 defendant entered into a subcontract with plaintiff for the
concrete, asphalt and paving work. The first paragraph of the subcontract
provided in relevant part:
"[T]he Subcontractor
agrees to furnish all material and perform all work . . . in accordance
with the general conditions, special conditions, plans, specifications,
and the Contract between the Contractor [plaintiff] and the Owner
[Durham County] . . . and the Subcontractor hereby agrees to be bound to
the Contractor by the terms of the above Contract, general conditions,
special conditions . . . and to assume toward the Contractor all the
obligations and responsibilities that the Contractor, by those
documents, assumes toward the Owner . . . ."
Similar provisions are also
provided in paragraph twenty-four of the subcontract. The third paragraph
of the subcontract provides:
"The Subcontractor
agrees that the time of performance is of the essence of this contract,
and further agrees to commence work when notified. The Subcontractor
[***4] further agrees to perform all work under this contract with all
possible dispatch, and to execute all work in such a manner as not to
delay any other Subcontractor or the Contractor in the general progress
of the whole work."
Page Four of the Subcontract
first identifies unit prices for the concrete, curb and asphalt paving
work, and then provides as follows:
"Acceptance of this
subcontract guarantees the above prices for the duration of the project.
Duration of the project is defined as being the original job time plus
any time extensions granted by the Owner."
The original time for
completion of the general contract was 1000 days, commencing 19 June 1972
and ending 15 March 1975. After several "Change Orders,"
however, the original time period was extended by 334 days.
The initial work schedule,
prepared after the subcontract was signed, showed that site improvements
including curb and gutter work were to be done August-October 1972 and
January-February 1975. A copy of this schedule was sent to defendant on 3
August 1972. Although other progress schedules were prepared, none were
sent to the defendant.
On 4 March 1975 plaintiff sent
defendant a letter asking defendant [***5] to set up a definite starting
time. In a letter dated 17 March 1975 defendant's counsel indicated that
the subcontract was terminated because of plaintiff's extreme delay in
requesting defendant's performance. On 5 May 1975 plaintiff again notified
defendant that defendant was to proceed with the work under the
subcontract. Defendant never set a starting date and never performed any
work. Plaintiff solicited another contract to do the gutter and asphalt
work and this second subcontractor was paid $ 25,314 more than defendant
would have been paid.
The defendant presented
evidence tending to show that defendant made its bid to work for the
plaintiff based on information given to it by the plaintiff, prior to the
time the subcontract was executed, that the paving work was to be done in
1972. The defendant's president, Oscar Miller, testified that the work
could not be started in 1972 because the site had not been graded. In
addition, the defendant's representatives went by the job site frequently
to find out if the site was ready. In late 1973, after defendant had
called upon plaintiff's job superintendent, defendant was told that the
curb and gutter work had been rescheduled [***6] for July and August of
1974. No notice to begin work, however, was received until 4 May 1975.
After both parties had
presented their evidence, the trial court entertained plaintiff's Rule 50
motion and directed a verdict in favor of the plaintiff on defendant's
counterclaim and in plaintiff's favor on plaintiff's damage claim for $
25,314.
COUNSEL:
Parker, Sink & Powers by
William H. Potter, Jr., for defendant appellant.
Poyner, Geraghty, Hartsfield
& Townsend by John J. Geraghty, David W. Long and Cecil W. Harrison,
Jr., for plaintiff appellee.
JUDGES:
Clark, Judge. Judges Hedrick
and Martin (Harry C.) concur.
OPINIONBY:
CLARK
OPINION:
[*600] [**288] The controlling
issue in this appeal is whether the defendant was bound by its subcontract
with plaintiff to perform when plaintiff asked defendant on 4 March 1975
to submit a starting time and when plaintiff gave defendant notice to
perform on 5 May 1975. "It is settled law that where the terms of a
written instrument or contract are explicit, the Court determines their
effect by declaring their legal meaning." Howland v. Stitzer, 240
N.C. 689, 696, 84 S.E. 2d 167 (1954). We now hold that defendant was
obligated to perform [***7] under its subcontract with plaintiff.
The critical facts have
already been set out. Notwithstanding any conversations defendant may have
had with the plaintiff prior to submission of defendant's bid, defendant
signed a subcontract in which defendant agreed: (1) to incorporate the
conditions of the general contract between plaintiff and Durham County,
including the provisions therein pertaining to the extension of time; (2)
to commence work "when notified" by the plaintiff; and (3) to
guarantee the quoted prices for the duration of the job "plus any
[*601] time extensions granted by the Owner." Plaintiff's request was
made within the original time period plus the 334-day time extension
granted by the Owner. Undoubtedly, plaintiff might have organized its
activities so as to place a lesser burden on defendant, but it was not
obligated under the subcontract to do so. Contracts are made for the
benefit of all parties to the contract. Each party assumes certain risks.
In this case defendant assumed both the risk that the cost of doing the
work would go up before the job would be completed and the risk that the
time for [**289] performing the work could be extended. Defendant [***8]
cannot now deny these self-assumed obligations, even if the course of
events prove them to be harsh. Weyerhaeuser v. Carolina Power & Light
Co., 257 N.C. 717, 722, 127 S.E. 2d 539 (1962).
We do not agree with defendant
that the language "for the duration of the job" was so ambiguous
as to make the subcontract unenforceable. The subcontract explicitly
defines the duration of the project as "the original job time plus
any time extensions granted by the Owner." Moreover, we think that
the context of the quoted language indicates that "job" refers
to the construction of the entire hospital complex and not just the curb
and gutter work.
The trial court's rulings on
plaintiff's motion for directed verdict on plaintiff's claim and
defendant's counterclaim are
Affirmed.