UNITED STATES FIDELITY &
GUARANTY COMPANY, a Maryland corporation v. CITY OF RALEIGH, a municipal
corporation
No. 8810SC649
COURT OF APPEALS OF NORTH
CAROLINA
93 N.C. App. 159; 376 S.E.2d
768; 1989 N.C. App. LEXIS 129
January 23, 1989, Heard in the
Court of Appeals
March 7, 1989, Filed
PRIOR HISTORY: [***1]
Appeal by plaintiff from
Stephens (Donald W.), Judge. Judgment entered 11 April 1988 in Wake County
Superior Court.
DISPOSITION:
Reversed and remanded.
PROCEDURAL POSTURE: Plaintiff
surety company challenged a judgment of the Wake County Superior Court
(North Carolina), which granted summary judgment against it in an action
against defendant municipality. The action arose from the municipality's
rejection of the surety company's bid bonds.
OVERVIEW: The municipality
argued that its actions were justified by a provision in the open bidding
procedure statute, N.C. Gen. Stat. § 143-129 (Cum. Supp. 1988), which
allowed a municipality to reject a licensed surety company's bid if it
failed to settle a pending claim against it within 180 days. The court
determined that the statute was punitive in nature and, therefore, had to
be strictly construed. The court concluded that the municipality's
authorization to reject a surety company's bonds existed only if it had
made a claim against that company that was currently pending and that had
been pending more than 180 days. The court rejected the municipality's
contention that its claim against the surety company for a contractor's
alleged breach of contract qualified as a "claim" under the
statute. That dispute was settled, and the statute contained no provision
for reviving claims after settlement. The surety company's subsequent
action against the municipality arising from that settlement did not
constitute a claim against the surety company. The court reversed and held
that the trial court erred in granting the municipality's motion for
summary judgment.
OUTCOME: The court reversed
the judgment and remanded for the entry of an order granting summary
judgment for the surety company to the effect that the municipality could
not use the contract dispute as a basis to reject the surety company's bid
bonds.
SYLLABUS:
Plaintiff is a Maryland
corporation authorized to do business in North Carolina. Defendant entered
a contract with NewKor Construction, Inc. for construction work on a
public project known as Glen Eden Pilot Park. Plaintiff, as surety for the
construction company under a performance bond, negotiated a settlement
agreement with defendant, after the latter declared NewKor to be in
default of the construction contract. The agreement required plaintiff to
advance $ 104,543 to defendant in full satisfaction of the latter's claims
involving completion [***3] of the project. These funds would be repaid to
plaintiff in full if the arbitrator resolving the dispute between
defendant and NewKor "determined from the evidence in the arbitration
proceeding [upon the arbitrator's findings of fact and conclusions of law
and in any final judgment based thereon, . . .]" that defendant had
wrongfully terminated its contract with NewKor.
The arbitrator awarded NewKor
$ 54,700, but made no specific finding that defendant had wrongfully
terminated the construction contract. Defendant refused to repay the money
advanced by plaintiff, and plaintiff filed an action in Wake County
Superior Court on 31 March 1987 to recover it. Defendant issued a
statement on 16 November 1987 that "bid bonds and/or performance
bonds written by the United States Fidelity and Guarantee [sic] Co., will
not be acceptable to the City of Raleigh."
Plaintiff filed this action
for a declaratory judgment and injunctive relief on 10 December 1987.
Judge Farmer entered a temporary restraining order preventing defendant
from barring plaintiff from participating in the bidding process or from
entering any public contracts from which plaintiff had been excluded on 10
December [***4] 1987. Both parties agreed that there were no outstanding
issues of material fact, and Judge Stephens granted defendant's motion for
summary judgment on 11 April 1988.
COUNSEL:
Bailey & Dixon, by J.
Ruffin Bailey, David M. Britt and Alan J. Miles, for plaintiff-appellant.
Poyner & Spruill, by John
L. Shaw and Donna Sisson Richter, for defendant-appellee.
JUDGES:
Wells, Judge. Judges Becton
and Johnson concur.
OPINIONBY:
WELLS
OPINION:
[*160] [**769] Plaintiff
appeals the entry of summary judgment against it, contending that it was
entitled to judgment as a matter of law. Defendant asserts that its action
was fully justified by that provision of the open bidding procedure
statute, N.C. Gen. Stat. § 143-129 (Cum. Supp. 1988), [HN1] which
authorizes rejecting bonds issued by surety companies in certain
situations.
[*161] The . . . governing
board, in contracts involving a political subdivision of the State, may
reject the bonds of any surety company against which there is pending
any unsettled claim or complaint made by a . . . governing board of any
political subdivision of the State arising out of any contract under
which State funds, in contracts with the State, or funds of political
subdivisions of the State, [***5] in contracts with such political
subdivision, were expended, provided such claim or complaint has been
pending more than 180 days.
Id.
This provision allows a
municipality to reject a licensed surety company's bid if it fails to
settle a pending claim against it within 180 days. It operates to prevent
a licensed surety company from engaging in the business it is otherwise
authorized to participate in under the laws of this State, N.C. Gen. Stat.
§ § 55-17, 55-140 (1982), and therefore is punitive in nature. [HN2]
Punitive statutes must be strictly construed. Jones [**770] v.
Georgia-Pacific Corp., 15 N.C. App. 515, 190 S.E. 2d 422 (1972).
Strict construction requires
that "[e]verything not clearly within the scope of the language . . .
be excluded from the operation of the [statute], taking the words in their
natural and ordinary meaning." City of Sanford v. Dandy Signs, Inc.,
62 N.C. App. 568, 303 S.E. 2d 228 (1983) (citing Harrison v. Guilford
County, 218 N.C. 718, 12 S.E. 2d 269 (1940)). Applying these principles,
[HN3] defendant's authorization to reject a surety company's bonds exists
only [***6] if it has made a claim against that company which is currently
pending, and which has been pending more than 180 days.
Defendant contends that its
claim against plaintiff for NewKor's alleged breach of contract qualifies
as a "claim" under the statute. Although the dispute was
settled, defendant argues that plaintiff reactivated its initial claim by
repudiating the settlement agreement. A narrow construction of the statute
does not support this interpretation. The statute contains no provision
for reviving claims after settlement, and no language suggests that a
surety company's subsequent action against a municipality arising from
their settlement constitutes a claim against the surety. Defendant cannot
invoke this provision to justify its blanket refusal to accept plaintiff's
bonds.
We hold that the trial court
erred in granting defendant's motion for summary judgment and remand for
the entry of an [*162] order granting summary judgment for plaintiff to
the effect that defendant cannot use the NewKor contract dispute as a
basis under the statute to reject plaintiff's bid bonds.
Reversed and remanded.