UNITED STATES FIDELITY & GUARANTY COMPANY, a Maryland corporation v. CITY OF RALEIGH, a municipal corporation

No. 8810SC649

COURT OF APPEALS OF NORTH CAROLINA

93 N.C. App. 159; 376 S.E.2d 768; 1989 N.C. App. LEXIS 129

January 23, 1989, Heard in the Court of Appeals

March 7, 1989, Filed

PRIOR HISTORY: [***1]

Appeal by plaintiff from Stephens (Donald W.), Judge. Judgment entered 11 April 1988 in Wake County Superior Court.

DISPOSITION:

Reversed and remanded.

PROCEDURAL POSTURE: Plaintiff surety company challenged a judgment of the Wake County Superior Court (North Carolina), which granted summary judgment against it in an action against defendant municipality. The action arose from the municipality's rejection of the surety company's bid bonds.

OVERVIEW: The municipality argued that its actions were justified by a provision in the open bidding procedure statute, N.C. Gen. Stat. § 143-129 (Cum. Supp. 1988), which allowed a municipality to reject a licensed surety company's bid if it failed to settle a pending claim against it within 180 days. The court determined that the statute was punitive in nature and, therefore, had to be strictly construed. The court concluded that the municipality's authorization to reject a surety company's bonds existed only if it had made a claim against that company that was currently pending and that had been pending more than 180 days. The court rejected the municipality's contention that its claim against the surety company for a contractor's alleged breach of contract qualified as a "claim" under the statute. That dispute was settled, and the statute contained no provision for reviving claims after settlement. The surety company's subsequent action against the municipality arising from that settlement did not constitute a claim against the surety company. The court reversed and held that the trial court erred in granting the municipality's motion for summary judgment.

OUTCOME: The court reversed the judgment and remanded for the entry of an order granting summary judgment for the surety company to the effect that the municipality could not use the contract dispute as a basis to reject the surety company's bid bonds.

SYLLABUS:

Plaintiff is a Maryland corporation authorized to do business in North Carolina. Defendant entered a contract with NewKor Construction, Inc. for construction work on a public project known as Glen Eden Pilot Park. Plaintiff, as surety for the construction company under a performance bond, negotiated a settlement agreement with defendant, after the latter declared NewKor to be in default of the construction contract. The agreement required plaintiff to advance $ 104,543 to defendant in full satisfaction of the latter's claims involving completion [***3] of the project. These funds would be repaid to plaintiff in full if the arbitrator resolving the dispute between defendant and NewKor "determined from the evidence in the arbitration proceeding [upon the arbitrator's findings of fact and conclusions of law and in any final judgment based thereon, . . .]" that defendant had wrongfully terminated its contract with NewKor.

The arbitrator awarded NewKor $ 54,700, but made no specific finding that defendant had wrongfully terminated the construction contract. Defendant refused to repay the money advanced by plaintiff, and plaintiff filed an action in Wake County Superior Court on 31 March 1987 to recover it. Defendant issued a statement on 16 November 1987 that "bid bonds and/or performance bonds written by the United States Fidelity and Guarantee [sic] Co., will not be acceptable to the City of Raleigh."

Plaintiff filed this action for a declaratory judgment and injunctive relief on 10 December 1987. Judge Farmer entered a temporary restraining order preventing defendant from barring plaintiff from participating in the bidding process or from entering any public contracts from which plaintiff had been excluded on 10 December [***4] 1987. Both parties agreed that there were no outstanding issues of material fact, and Judge Stephens granted defendant's motion for summary judgment on 11 April 1988.

COUNSEL:

Bailey & Dixon, by J. Ruffin Bailey, David M. Britt and Alan J. Miles, for plaintiff-appellant.

Poyner & Spruill, by John L. Shaw and Donna Sisson Richter, for defendant-appellee.

JUDGES:

Wells, Judge. Judges Becton and Johnson concur.

OPINIONBY:

WELLS

OPINION:

[*160] [**769] Plaintiff appeals the entry of summary judgment against it, contending that it was entitled to judgment as a matter of law. Defendant asserts that its action was fully justified by that provision of the open bidding procedure statute, N.C. Gen. Stat. § 143-129 (Cum. Supp. 1988), [HN1] which authorizes rejecting bonds issued by surety companies in certain situations.

[*161] The . . . governing board, in contracts involving a political subdivision of the State, may reject the bonds of any surety company against which there is pending any unsettled claim or complaint made by a . . . governing board of any political subdivision of the State arising out of any contract under which State funds, in contracts with the State, or funds of political subdivisions of the State, [***5] in contracts with such political subdivision, were expended, provided such claim or complaint has been pending more than 180 days.

Id.

This provision allows a municipality to reject a licensed surety company's bid if it fails to settle a pending claim against it within 180 days. It operates to prevent a licensed surety company from engaging in the business it is otherwise authorized to participate in under the laws of this State, N.C. Gen. Stat. § § 55-17, 55-140 (1982), and therefore is punitive in nature. [HN2] Punitive statutes must be strictly construed. Jones [**770] v. Georgia-Pacific Corp., 15 N.C. App. 515, 190 S.E. 2d 422 (1972).

Strict construction requires that "[e]verything not clearly within the scope of the language . . . be excluded from the operation of the [statute], taking the words in their natural and ordinary meaning." City of Sanford v. Dandy Signs, Inc., 62 N.C. App. 568, 303 S.E. 2d 228 (1983) (citing Harrison v. Guilford County, 218 N.C. 718, 12 S.E. 2d 269 (1940)). Applying these principles, [HN3] defendant's authorization to reject a surety company's bonds exists only [***6] if it has made a claim against that company which is currently pending, and which has been pending more than 180 days.

Defendant contends that its claim against plaintiff for NewKor's alleged breach of contract qualifies as a "claim" under the statute. Although the dispute was settled, defendant argues that plaintiff reactivated its initial claim by repudiating the settlement agreement. A narrow construction of the statute does not support this interpretation. The statute contains no provision for reviving claims after settlement, and no language suggests that a surety company's subsequent action against a municipality arising from their settlement constitutes a claim against the surety. Defendant cannot invoke this provision to justify its blanket refusal to accept plaintiff's bonds.

We hold that the trial court erred in granting defendant's motion for summary judgment and remand for the entry of an [*162] order granting summary judgment for plaintiff to the effect that defendant cannot use the NewKor contract dispute as a basis under the statute to reject plaintiff's bid bonds.

Reversed and remanded.