ALLAN MILES COMPANIES, INC.,
ALLAN D. MILES and WANDA M. MILES, and BEN B. PROPST CONTRACTOR, INC. v.
NORTH CAROLINA DEPARTMENT OF TRANSPORTATION
No. 8319SC719
COURT OF APPEALS OF NORTH
CAROLINA
68 N.C. App. 136;
314 S.E.2d 576; 1984 N.C.
App. LEXIS 3193
April 12, 1984, Heard in the
Court of Appeals
May 1, 1984, Filed
PRIOR HISTORY: [***1]
Appeal by plaintiff from Freeman,
Judge. Judgment entered 11 April 1983 in Superior Court, Cabarrus
County.
DISPOSITION:
Affirmed.
OVERVIEW: The
landowners negotiated a proposed agreement with the Department for the
conveyance of an easement for utility lines across their property to a
pair of highway rest areas. The agreement included the allocation of costs
for extending existing water and sewer lines on the landowners' property.
The Department later abandoned its plans, and it tendered a certain amount
in settlement of the expenses incurred by the landowners for work done
solely for the Department. The landowners refused the tender, and the
Department refused to pay the contractor for its work. Plaintiffs filed a
breach of contract action against the Department. The trial court granted
summary judgment to the Department. On appeal, the court held that
plaintiffs' claim was barred by N.C. Gen. Stat. § 136-29 because
they did not first present their claim to the State Highway Administrator
and thus, they failed to exhaust their administrative remedies. The court
also held that the existence of a factual issue on the contracts'
existence was immaterial because it clearly appeared on the face of the
record that the claim was barred by § 136-29 and thus, the Department was
entitled to judgment as a matter of law.
OUTCOME: The
court affirmed the trial court's decision.
All plaintiffs appealed.
COUNSEL:
Attorney General Rufus L.
Edmisten [***3] by Assistant
Attorney General Thomas H. Davis, Jr. for North Carolina Department of
Transportation, defendant appellee.
Tom M. Grady and William F.
Rogers, Jr. for Allan Miles Companies, Inc., Allan D. Miles and Wanda M.
Miles, plaintiff appellants.
K. Michael Koontz and William
F. Rogers, Jr. for Ben B. Propst Contractor, Inc., plaintiff appellant.
JUDGES:
Cecil J. Hill, Judge, wrote
the opinion. Judges John Webb and Willis P. Whichard concur.
OPINIONBY:
HILL
OPINION:
[*137] [**577] The sole
question presented on appeal is whether the trial court erred in granting
summary judgment for defendant. Resolution of this issue involves
determination of (1) whether the parties' contractual dispute created a
genuine issue of material fact, and (2) whether plaintiffs' claim was
barred by statute and operation of law. Because it clearly appears G.S.
136-29 operates to bar plaintiffs' claim, we conclude defendant was
entitled to summary judgment as a matter of law.
(1) The contract.
Plaintiffs Allan D. Miles and his wife, Wanda M. Miles, are the record
owners of a tract of land located adjacent to a pair of rest areas on I-85
in Cabarrus County and owned by the Department [***4] of Transportation.
The two of them are president and secretary respectively of the corporate
plaintiff Allan Miles Companies, Inc. Plaintiff Ben B. Propst Contractor,
Inc. is a private contracting firm. Ernest D. Ransdell is the area utility
agent for the North Carolina Department of Transportation.
[*138] Ransdell and Allan D.
Miles negotiated a proposed agreement whereby Allan D. Miles and wife,
Wanda M. Miles, would convey to the defendant Department of Transportation
a permanent easement for telephone, water, and sewer lines across their
property to the I-85 rest areas. A letter from Ransdell to Allan Miles
dated 30 July 1980 provided substantially as follows: Plaintiff Miles
Companies would extend an eight inch water main from an existing main on
one of the properties of Allan D. Miles and wife to a designated point in
Bridlewood Place at an estimated cost to plaintiff of $ 57,490.00.
Defendant would bear one-half of the cost. From that point defendant was
to procure construction and installation of a six inch water main across
the property of Allan D. Miles and wife to defendant's property at an
estimated cost of $ 7,608.00.
Plaintiff Miles Companies
would extend [***5] the line from an existing sewer line in Overlook
Subdivision owned by Allan D. Miles and wife to a point in Bridlewood
[**578] Place at an estimated cost to plaintiff Miles Companies of $
55,610.00. Defendant would bear all the costs of this line. From that
point the defendant would extend at its own expense the sewer line along
Bridlewood Place and plaintiff's property at an estimated cost of $
8,558.00. The final paragraph of the letter stated:
Please submit the estimate
and plans for the work indicated above, at your earliest convenience,
and we will proceed with preparing the necessary reimbursement
agreement. If you should have questions or need additional information
concerning the above, please let me know.
Another letter dated 31 July
1980 was sent to Allan Miles as president of Allan Miles Companies, Inc.,
from the State utility agent amending the location of the sewer line.
Again the letter stated, "I will proceed with preparing the
reimbursement as soon as Mr. Billups submits your estimate and
plans." Another letter was addressed to Allan Miles from the State
utility agent dated 4 August 1980 amending the description of the location
of the property lines. [***6]
On 8 August 1980, J. H.
Craver, president of Ben B. Propst Contractor, Inc., submitted a proposal
to install the eight inch and six inch water lines, and to extend the
sewer line. Thereafter on [*139] 24 November 1980 the State utility agent
wrote Allan Miles as follows:
Subject: Water and Sewer
Service to Proposed Rest Areas
Dear Mr. Miles:
This letter will confirm our
telephone conversation of November 14, 1980, wherein the following items
were discussed:
1. It was agreed that the
Division of Highways will abandon plans, both for now and the future,
to tie water and sewer service lines from our proposed rest area sites
into existing water and sewer lines in your Partridge Bluff and
Overbrook Subdivisions.
2. The Division of
Highways will reimburse you for the cost of making certain water and
sewer line adjustments solely for the benefit of the Division. These
adjustments, which were shown as numbered paragraphs two (2) and four
(4) in Mr. J. H. Craver's letter of August 8, 1980, to you, were
estimated to cost $ 16,971.00. A copy of Mr. Craver's letter is
attached for your information.
3. You agreed to submit to
this office an itemized bill [***7] covering the costs mentioned in
item two (2) above. Please detail the bill to show a breakdown of the
amount and type of the various items of material used and any other
cost involved, such as rock excavation, etc. I advised you that the
bill would be audited prior to payment and you agreed to provide our
auditors documentation of the costs and allow them to examine your
records when requested.
4. You agreed to nullify
any agreements that you felt you had with the Division of Highways and
not pursue further any claims against the Division associated with any
such agreements. This includes, but is not limited to, the items
included in my letters of July 30 and 31, 1980, to you. A copy of each
of the letters is attached for your use.
If you are in agreement with
the foregoing, please advise. Also, please submit the bill for the
actual cost of the work indicated in item two (2) above.
[*140] On 17 December 1980,
Allan Miles replied to the State utility agent as follows:
In reply to your letter
dated November 24, 1980, I am not in agreement with your proposal and
request payment according to your letter of intent dated July 30th, and
amended July 31, [***8] 1980. Easements, estimates and plans as you
requested in your July 30th letter may be obtained from Mr. Johnny
Graham, P. E. Staff Engineer, Security Real Estate, 476 Church Street
N., Concord, North Carolina 28025.
The State utility agent
replied by letter dated 13 January 1981 stating:
[**579] In our last meeting
of September 23, 1980, you advanced the proposal that the Division of
Highways not tie water and sewer service lines from the proposed rest
areas into existing lines within your Partridge Bluff and Overbrook
Subdivisions. In addition, you proposed that the rest areas be served
from some point that would not involve your property. Accordingly, we
abandoned plans to tie into water and sewer lines located on your
property and have made plans to receive water and sewer service from
another direction. This is in keeping with both the meeting mentioned
above and our telephone conversation of November 14, 1980, with you.
Thereafter, the defendant
offered to submit a check as full and complete settlement of all expenses
incurred by Miles for work done solely for the Division of Highways in
accordance with an itemized statement attached to Miles' letter [***9]
dated 17 December 1980 totalling $ 16,971.00. Miles refused to accept
defendant's offer.
In the meantime plaintiff
Miles Companies had installed the eight inch water main at the cost of $
57,490.00 and the sewer line for a cost of $ 55,610.00, and plaintiff
Propst had extended the six inch water main at a cost of $ 16,166.00.
Defendant refused to reimburse plaintiff Miles Companies for one-half the
cost of installing the eight inch water main and the total cost of the
sewer line. Defendant also refused to pay plaintiff Propst Contractor,
Inc. for the work performed by it.
No competitive bidding was
held for any of the work described herein. Nor were any claims filed with
Billy Rose, State [*141] highway administrator, prior to initiation of the
action in superior court.
All plaintiffs have alleged
the existence of contracts with the State Department of Transportation,
and defendant has denied the existence of such contracts. Such constitutes
a genuine issue of fact. However, [HN1] when the question of fact
presented is immaterial, entry of summary judgment is not prevented. Keith
v. Reddick, Inc., 15 N.C. App. 94, 189 S.E. 2d 775 (1972). In the case
under review, the [***10] issue of fact as to the parties' contract
becomes immaterial because [HN2] where it clearly appears on the face of
the record that a plaintiff's claim is barred by statute or operation of
law, the moving party is entitled to summary judgment as a matter of law. Jarrell
v. Sampsonite Corp., 12 N.C. App. 673, 184 S.E. 2d 376 (1971), cert.
denied, 280 N.C. 180, 185 S.E.
2d 704 (1972).
(2) G.S. 136-29.
Defendant contends summary judgment was proper, asserting that G.S.
136-29 is a condition precedent to the institution of this action by
all plaintiffs. Defendant argues the trial court lacked subject matter
jurisdiction in this case because of plaintiff's failure to exhaust their
administrative remedies. We agree.
The North Carolina Department
of Transportation is an agency of the State of North Carolina, and as such
is subject to sovereign immunity, when such immunity is not waived. Orange
County v. Heath, 14 N.C. App. 44, 187 S.E. 2d 345, aff'd 282
N.C. 292, 192 S.E. 2d 308 (1972). The North Carolina Legislature has
waived sovereign immunity with respect to disputes between contractors and
the North Carolina Department of Transportation by the enactment of G.S.
[***11] 136-29 entitled, "Adjustment of Claims."
[HN3] This statute reads in part as follows:
(a) Upon the completion of
any contract for the construction of any State highway awarded by the
Department of Transportation to any contractor, if the contractor fails
to receive such settlement as he claims to be entitled to under his
contract, he may, within 60 days from the time of receiving his final
estimate, submit to the State Highway Administrator a written and
verified claim for such amount as he deems himself entitled to under the
said contract setting forth the facts upon which said claim is based. .
. .
[*142] (b) As to such
portion of the claim as is denied by the State Highway Administrator,
the contractor may, within six (6) months from receipt of said decision,
institute [**580] a civil action for such sum as he claims to be
entitled to under said contract by the filing of a verified complaint
and issuance of summons in the Superior Court of Wake County or in the
superior court of any county wherein the work under said contract was
performed. . . .
(c) All issues of law and
fact and every other issue shall be tried by the judge, without a jury.
. . .
[HN4] (d) [***12] The
submission of the claim to the State Highway Administrator within the
time and as set out in subsection (a) of this section and the filing of
an action in the superior court within the time as set out in subsection
(b) of this section shall be a condition precedent to bringing such an
action under this section and shall not be a statute of limitations.
(e) The provisions of this
section shall be deemed to enter into and form a part of every contract
entered into between the Department of Transportation and any
contractor, and no provision in said contracts shall be valid that is in
conflict herewith.
Plaintiffs contend that the
contracts between the parties are not contracts for the construction of a
state highway, and G.S. 136-29 has no application to the facts of
this case. In support of their position, plaintiffs Allan D. Miles and
Wanda M. Miles and Miles Companies point out that defendant bargained to
acquire two thirty foot permanent rights of way without cost and to
"reimburse" plaintiffs for their costs of installing water and
sewer lines in said rights of way over their property toward the proposed
highway rest areas. Plaintiffs contend this constituted, [***13] in
effect, a sale of easements. Plaintiff Ben B. Propst contends his
installation of water and sewer lines does not constitute
"construction and repair of the highway rest area buildings and
facilities" covered by the statute. We disagree with plaintiffs'
contentions and affirm the decision of the trial judge.
The sole need for the water
and sewer lines is to service the two rest areas adjoining I-85. Rest
areas are an accepted part of the modern highway system. They not only
provide comfort for [*143] the traveller, but also promote highway safety
by serving the physical needs of the traveller. [HN5] "The
construction and repair of the highway rest area buildings . . . shall be
deemed highway construction or repair. . . ." G.S. 136-28.1(d).
In order to provide permanent access to the Concord utility system,
plaintiff Miles agreed to give the right of way for the water and sewer
lines. The water and sewer lines per se as installed became a part
of the rest stop facility which they served. The raison d'etre for
the lines was to provide this service as a part of the rest stop facility,
which was a part of the highway system.
We conclude the contracts fall
within the [***14] provisions of G.S. 136-29. The language of the
statute clearly sets out that the presentation of a "claim to the
State Highway Administrator . . . shall be a condition precedent to
bringing such an action under this section." G.S. 136-29(d); In
re Huyck Corp. v. Mangum, Inc., 309 N.C. 788, 309 S.E. 2d 183 (1983).
Plaintiffs have failed to pursue their administrative remedies and have no
standing in court. Presnell v. Pell,
298 N.C. 715, 260 S.E. 2d 611 (1979).
The decision of the trial
judge is
Affirmed.