BARRUS CONSTRUCTION COMPANY, a
division of APAC-CAROLINA, INC. v. NORTH CAROLINA DEPARTMENT OF
TRANSPORTATION
No. 8411SC195
COURT OF APPEALS OF NORTH
CAROLINA
71 N.C. App. 700;
324 S.E.2d 1; 1984 N.C. App.
LEXIS 3971
November 13, 1984, Heard in
the Court of Appeals
December 18, 1984, Filed
PRIOR HISTORY: [***1]
Appeal by plaintiff from Bailey,
Judge. Judgment entered 16 November 1983 in Johnston County Superior
Court.
DISPOSITION:
Affirmed.
OVERVIEW: The
construction company's suit against the DOT was initiated and summons was
issued within the time set by the statute, but the construction company
failed to properly serve the DOT's registered process agent or the
attorney general as required by N.C. Gen. Stat. § 1A-1. After the
six-month period had expired, but only 35 days after issuance of the
original summons, the construction company obtained an alias or pluries
summons, which was properly served in due time on the DOT. The trial court
denied the DOT's motion to dismiss, holding that the construction
company's alias summons continued the action. The court held that N.C.
Gen. Stat. § 136-29 only required institution of the civil action
within six months, not service of process. The court determined that there
was no evidence that the original summons designated the wrong defendant,
only that it was incorrectly served. The court held that dismissal was
improper because the company timely continued its action against the DOT.
The court held that the DOT was entitled to summary judgment, however,
because the contract contained no ambiguities. The court affirmed the
judgment of the trial court.
OUTCOME: The
court affirmed the judgment of the trial court, which denied the DOT's
motion to dismiss the construction company's suit on its highway contract
claim for insufficient service of process but granted summary judgment in
favor of the DOT.
COUNSEL:
White, Allen, Hooten &
Hodges, P.A., by John C. Archie, for plaintiff.
Attorney General Rufus L.
Edmisten, by Assistant Attorney General Thomas H. Davis, Jr., for
defendant.
JUDGES:
Hugh A. Wells, Judge, wrote
the opinion. Judges Gerald Arnold and Charles L. Becton concur.
OPINIONBY:
WELLS
OPINION:
[*703] [**2] We address first
the DOT's cross assignment of error that service of process was not timely
and that the court erred in denying its motion to dismiss. [HN1] The state
has consented to suit on highway contract claims. N.C. Gen. Stat. §
136-29 (1981 and Cum. Supp. 1983). Such a suit is timely filed if
instituted by filing of complaint and issuance of summons within six
months after the final decision of the State Highway Administrator denying
the claim. Id. Plaintiff filed its complaint, and summons issued,
within the time set by statute. However, the summons was not properly
served on the DOT's registered process agent or the Attorney General as
required by N.C. Gen. Stat. § 1A-1, Rule 4(j)(4) of the Rules of
Civil Procedure [***6] (1983). After the six-month period had expired, but
only 30 days after issuance of the original summons, the DOT moved to
dismiss. Five days later, and 35 days after issuance of the original
summons, plaintiff obtained an alias or pluries summons which was properly
served in due time on the DOT. The trial court ruled that the alias
summons continued the action and denied the DOT's motion. We affirm that
ruling.
[HN2] G.S. § 136-29
only requires institution of the civil action, not service of process,
within six months. N.C. Gen. Stat. § 1A-1, Rule [**3] 4(d) of the
Rules of Civil Procedure (1983) provides that a civil action may be
continued in existence against "any defendant" (emphasis
added) by suing out alias summons within 90 days of the last preceding
summons. No special attention to this rule appears for suits against the
state, nor does this civil action appear to be any different from other
civil actions. The state, once it has consented [*704] to suit, occupies
the same position as any other litigant. Smith v. State, 289 N.C. 303,
222 S.E. 2d 412 (1976). There is no indication that the original
summons designated the wrong defendant, only that it was [***7]
incorrectly served. Compare Roshelli v. Sperry, 57 N.C. App. 305, 291
S.E. 2d 355 (1982) (correcting summons to name correct defendant
institution of new action). We therefore hold that although the first
service was of no effect, Stone v. Hicks, 45 N.C. App. 66, 262 S.E. 2d
318 (1980), plaintiff timely continued its action in existence and
dismissal was improper. Rule 4(d); Williams v. Bray, 273 N.C. 198, 159
S.E. 2d 556 (1968); see also Consolidation Coal Co. v. Disabled
Miners of So. W. Va., 442 F. 2d 1261 (4th Cir.), cert. denied, 404
U.S. 911 (1971) (error to dismiss where second, correct service
timely). The court had jurisdiction and correctly denied the DOT's motion.
Turning now to the merits, we
note that [HN3] summary judgment may be granted to the non-moving party in
appropriate cases. A-S-P Associates v. City of Raleigh,38 N.C. App.
271, 247 S.E. 2d 800 (1978), rev'd on other grounds, 298
N.C. 207, 258 S.E. 2d 444 (1979). Where dispute arises only as to
questions of law, summary judgment is appropriate. Kessing v. Mortgage
Corp., 278 N.C. 523, 180 S.E. 2d 823 (1971). Both parties concede in
their briefs that there is no dispute concerning [***8] any material fact.
[HN4] "When a contract is in writing and free from any ambiguity
which would require resort to extrinsic evidence, or the consideration of
disputed fact, the intention of the parties is a question of law. The
court determines the effect of their agreement by declaring its legal
meaning." Lane v. Scarborough, 284 N.C. 407, 200 S.E. 2d 622
(1973); see also Salvation Army v. Welfare, 63 N.C. App. 156, 303
S.E. 2d 658 (1983), disc. rev. denied, 311 N.C. 306, 317
S.E. 2d 682 (1984); 4 S. Williston, Law of Contracts § 616 (3d ed.
1961); Restatement (Second) of Contracts § 200, Comment c. (1981).
Since this contract is in writing, and the facts are undisputed, its legal
effect was for the court and summary judgment was appropriate.
Plaintiff's position is
simple: since the contract expressly provides that there will be a 180-day
inspection period after the intermediate completion date, the DOT,
in adjusting the intermediate date, was required to correspondingly adjust
the final contract completion date to reflect the 180-day interval.
Therefore, plaintiff and not the DOT was entitled to judgment. We
disagree.
[*705] First, the contract
sets intermediate [***9] and final contract time separately, and sets
liquidated damages separately for overruns of each date. Second, it
separately provides that intermediate completion dates "may be
extended on the same basis as [final] completion dates . . . ."
Nowhere does the contract require that extensions to the intermediate date
be matched exactly by extensions to the final date. Rather, it simply
provides that such extensions may be made. Third, it provides that
extensions of time or remittances of damages for delay shall be "only
to the extent and in the proportion that such delays were caused by the
conditions set forth in [the section describing good cause for which the
DOT would grant extensions]." The contract thus clearly reflects an
intent to allow the DOT discretion in adjusting extensions to avoid
unfairness.
The undisputed facts show that
even before its request for an extension, plaintiff had accepted unequal
extensions of the intermediate and final dates. In fact, the original
dates agreed upon were 166 days apart, although the DOT later adjusted the
final contract date to reflect the proper interval as part of its response
to plaintiff's original verified claim. Plaintiff [***10] then stipulated
[**4] to separate groups of "authorized time extensions" for the
two contract dates. Only one of the items appears as an extension to both
dates. The major item of difference, a 90-day winter weather extension,
was added only to the intermediate date in adherence to the terms of the
contract, which provides that upon authorized extension beyond 15 December
the 90 days is added automatically to the contract time. The final
contract date, however, was not extended beyond 15 December and thus did
not receive the 90-day extension. Plaintiff does not object to this
discrepancy, insisting instead on the inflexibility of the 180-day
interval.
It is apparent however from
both the plaintiff's claim and the DOT's answers to interrogatories that
adjustments to contract time reflect in large part contract, and not
actual, time. By the time plaintiff submitted its claim, it had already
completed the work, subject only to possible correction of pavement
markings. Plaintiff was already in breach under the terms of the contract;
allowing extensions served only to reduce the amount of damages assessed,
not to extend time to complete the work. Even accepting plaintiff's
[***11] requested extensions in toto, substantial damages would
still be due. The distinction between contract time and actual [*706] time
is crucial. We note that the DOT, in adjusting contract time, did correct
the original mistake in setting the interval 166 days. Contract time thus
properly allowed 180 days. The adjustments made, while generally
reflecting actual delays, did not correspond exactly to work in the field
as plaintiff contends.
The 90-day adjustment
mentioned above is one example; plaintiff received it even though it is
clear from the record that work continued during the period 15 December-16
March. Plaintiff arrived at several components of its request for
extension not by computing actual delays, but by calculations such as
multiplying the ratio (cost overruns/contract price) times contract time
to arrive at an estimated extension, or by estimating production
percentage shortfalls and requesting extensions by multiplying that
percentage times the days of production slowdown. Of special note in light
of plaintiff's present position is its request, thus arrived at, for a
192-day interval between the intermediate and final contract dates.
The DOT's explanations [***12]
for the extensions allowed similarly reflect contract adjustments. The DOT
adopted the same methodology as plaintiff in computing overrun and
underrun extensions. It used a "theoretical pro rata basis" in
these calculations. In addition it adjusted the final date based on
percentage modifications of the arbitrary winter extension period. It is
clear from all this evidence that the adjustments in contract time after
breach were to properly adjust damages, not to change actual time of
performance.
Plaintiff does not contend
that any of the extensions granted by the DOT are unjustifiably small. Nor
does it contend that any specific adjustment should have been made which
was not made. Nor does it contend that by assessing liquidated damages for
overruns of both the intermediate and final contract dates, the DOT
unfairly doubled the damages. It admits that the erroneous interval in the
original contract has been corrected. Its only contention, simply put, is
that, having received a more favorable extension of the intermediate date
than the final date, it is entitled to an equal adjustment to the final
date. In light of the distinction between contract time and actual time
discussed [***13] above, the DOT could have simply used its
"theoretical pro rata" extensions and the like to add extension
days equally to both dates, leaving the [*707] same number of days'
delay and yet keeping the 180-day interval. Under the circumstances, we
conclude that on this record, defendant was entitled to summary judgment.
Affirmed.