LEDBETTER BROTHERS, INC., and
HARTFORD ACCIDENT AND INDEMNITY COMPANY v. THE NORTH CAROLINA DEPARTMENT
OF TRANSPORTATION
No. 8310SC192
COURT OF APPEALS OF NORTH
CAROLINA
68 N.C. App. 97;
314 S.E.2d 761; 1984 N.C.
App. LEXIS 3208
January 19, 1984, Heard in the
Court of Appeals
May 1, 1984, Filed
PRIOR HISTORY: [***1]
Appeal by plaintiffs from Brannon,
Judge. Judgment entered 6 October 1982 in Superior Court, Wake County.
DISPOSITION:
Affirmed.
OVERVIEW: On
appeal from the trial court's dismissal of the contractor's and surety's
claims, the court held that, under the language of the contract between
the sub-contractor and the DOT, neither the contractor nor the surety, as
a subrogor of the sub-contractor, could institute an action against the
DOT. The contract between sub-contractor and the contractor contained a
"hold harmless" clause that constituted an indemnity whereby the
sub-contractor and later the surety agreed to assume secondary liability
in the event a claim by the contractor against the DOT failed. The
contractor did, in fact, have standing to challenge the DOT's assessment
of liquidated damages. However, the liquidated damages were properly
assessable until the time the project was finally accepted. The liquidated
damages were not an unenforceable penalty. The liquidated damage amount
was a reasonable estimate of the damages and was proportionate to the
actual damages. Thus, the withholding of the liquidated damages by the DOT
was proper.
OUTCOME: The
court affirmed the trial court's order dismissing the action and upholding
the DOT's withholding of the liquidated damages.
COUNSEL:
Moore, Van Allen and Allen, by
Arch [***3] T. Allen, III and
Joseph W. Eason, for plaintiff appellants.
Attorney General Edmisten, by
Assistant Attorney General Thomas H. Davis, Jr., for defendant appellee.
JUDGES:
Charles L. Becton, Judge,
wrote the opinion. Judges Gerald Arnold and Willis P. Whichard concur.
OPINIONBY:
BECTON
OPINION:
[*98] [**763] This case
involves a challenge, by a general contractor and the surety for a
subcontractor on a State highway project, to a Superior Court judgment
upholding the Department of Transportation's (DOT's) assessment of
liquidated damages from contract retainages. We affirm the judgment.
I
Ledbetter Brothers (Ledbetter)
entered into a general contract with the DOT to perform some $ 3,300,000
in highway renovation. The work was to be completed by 1 December 1977.
Part of it involved moving and replacing signs and guardrails. Ledbetter
subcontracted the sign and guardrail work to SMS, Inc. (SMS), and, as
required by the general contract, SMS provided a performance bond issued
by Hartford Accident and Indemnity Company (Hartford) guaranteeing its
performance.
The sign and guardrail work
was not completed by the contract date, although the highway was open to
the public. [***4] SMS completed the guardrail work by 5 January 1978, and
it relocated and replaced all required signs by 16 February 1978. Shortly
after 16 February 1978, the DOT inspected the new and relocated signs and
found many of them to be defective and, accordingly, rejected [*99] them.
In particular, reflectorized replacement signs were not sufficiently
legible at night. At about the same time, SMS defaulted on the work
remaining under the subcontract (including replacement and correction of
the rejected signs), filed bankruptcy, and abandoned work on the project.
Hartford, as surety for SMS, arranged to have the defective work
corrected, and the DOT accepted the project on 15 May 1978.
The general contract contained
a liquidated damages provision which stipulated damages at a rate of $
300.00 per day. Upon final payment to Ledbetter in December 1978, the DOT
withheld $ 49,500.00, representing damages at the contract rate for the
165 days from 1 December 1977 to 15 May 1978. Ledbetter and Hartford
sought recovery of the liquidated damages by administrative appeal. The
claim was disallowed by the DOT on 20 July 1979. Ledbetter and Hartford
then brought the present action in Wake [***5] County Superior Court. The
trial court, sitting as trier of fact, found the liquidated damages
withheld valid and proper, and dismissed the claims, finding that neither
party had standing in any event. From this judgment, Ledbetter and
Hartford appeal.
II
We first address the standing
questions. The trial court found that Ledbetter had assigned its
unliquidated claim to Hartford, and that, therefore, Hartford was the real
party in interest. It found that such an assignment was void under N.C.
Gen. Stat. § 147-62 (1983), the "anti-assignment" statute;
that Hartford did not have any subrogation rights against the DOT; and
that Hartford, therefore, could not sue the DOT. Apparently because
Ledbetter was not the real party in interest, the trial court ruled that
Ledbetter's claim should be dismissed. Ledbetter and Hartford complain
that this ruling places them in an untenable "catch-22"
situation. We agree only as to Ledbetter, and hold that Ledbetter had
[**764] standing to sue and hence to bring the present appeal.
A.
The contract entered into
between Ledbetter and the DOT included by reference the Standard
Specifications for Roads and Structures (1972) (SRSS) issued [***6] by the
North Carolina State Highway Commission, DOT's predecessor. These
specifications contain the following provision, SSRS § 108-6:
[*100] The Contractor shall
not sublet, sell, transfer, assign, or otherwise dispose of the contract
or any portion thereof, or of his right, title, or interest therein,
without written consent of the Engineer. . . . The approval of any
subcontract will not release the Contractor of his liability under the
contract and bonds, nor will the Subcontractor have any claim against
the Commission by reason of the approval of the subcontract.
This Court has recently and
clearly interpreted this language to mean that had SMS itself remedied the
defective work, it would have had no cause of action against the DOT, nor
would Ledbetter be entitled to bring such a suit in SMS' behalf, to
recover liquidated damages. Warren Bros. Co. v. Dep't of Transp., 64
N.C. App. 598, 307 S.E. 2d 836 (1983). Does Hartford, which remedied
the defective work in SMS' behalf as its surety, have a better right?
Hartford argues that having
performed in the stead of SMS, it has, by subrogation, a right to proceed
against the liquidated damages retained [***7] by the DOT. [HN1]
"Subrogation is the substitution of one person in the place of
another with reference to a lawful claim or right. . . . A party can
acquire no better right by subrogation than that of the principal." Dowdy
v. Southern Ry. Co., 237 N.C. 519, 525, 75 S.E. 2d 639, 643 (1953); see
also Employers Mut. Cas. Co. v. Griffin, 46 N.C. App. 826, 266 S.E. 2d 18,
disc. rev. denied, 301 N.C. 86 (1980). When Hartford
completed the work which SMS had contracted to do, it therefore acquired
no cause of action against the DOT. Warren Bros. Co. v. Dep't of Transp.
As surety for SMS, the defaulting principal, Hartford could also attempt
to recover its payments from the estate of the bankrupt. See generally
74 Am. Jur. 2d Suretyship § § 168-177 (1974). However,
Hartford has shown no authority for its assertion that it is entitled to
recover against the DOT itself, and therefore the ruling dismissing its
claim was correct.
B.
With respect to the dismissal
of Ledbetter's claim, on the other hand, the trial court committed error.
The contract between SMS and Ledbetter contained a "hold
harmless" clause. Subsequent to the default of SMS, Ledbetter and
Hartford [***8] entered into an agreement incorporating a similar
provision. The trial court apparently confused these provisions with the
separate obligation [*101] on the part of SMS and then Hartford to
actually complete the work, and ruled that they constituted a void
assignment of a claim against the State under G.S. § 147-62
(1983), the "anti-assignment" statute. [HN2] That statute
provides in relevant part:
All transfers and
assignments made of any claim upon the State of North Carolina or any of
its departments, bureaus or commissions or upon any State institution or
of any part or share thereof or interest therein, whether absolute or
conditional and whatever may be the consideration therefor and all
powers of attorney, orders or other authorities for receiving payment of
any such claim or any part or share thereof shall be absolutely null and
void unless such claim has been duly audited and allowed and the amount
due thereon fixed and a warrant for the payment thereof has been issued;
and no warrant shall be issued to any assignee of any claim or any part
or share thereof or interest therein . . . .
The appellate courts of this
State have not construed this language to [***9] date. However, certain
principles are clear. [HN3] An "assignment" involves a transfer
from one to another, usually in exchange for some consideration. Black's
Law Dictionary 109 (5th [**765] ed. 1979); Morton v. Thornton, 259
N.C. 697, 131 S.E. 2d 378 (1963). The "hold harmless"
agreements did not purport to assign or transfer anything; rather they
constituted an indemnity, whereby SMS and later Hartford agreed to assume
secondary liability in the event a claim by Ledbetter against the DOT
failed. See New Amsterdam Cas. Co. v. Waller, 233 N.C. 536, 64 S.E. 2d
826 (1951); 41 Am. Jur. 2d Indemnity § § 3-4 (1968).
Neither the record nor the agreement itself suggests that Hartford has
actually paid Ledbetter pursuant to the hold harmless agreement. It is
elementary that as long as Ledbetter remained unpaid, even in part, it
remained a real party in interest, as our courts have uniformly held in
indemnity (particularly insurance) cases. See e.g. Sec. Fire &
Indem. Co. v. Barnhardt, 267 N.C. 302, 148 S.E. 2d 117 (1966); Taylor
v. Green, 242 N.C. 156, 87 S.E. 2d 11 (1955). We find nothing in the
"anti-assignment" statute to change this rule, nor does the
policy [***10] behind such statutes require that an unpaid indemnitee
(Ledbetter) be precluded from bringing its claim. See United States v.
Aetna Cas. & Sur. Co., 338 U.S. 366, 94 L.Ed. 171, 70 S.Ct. 207 (1949)
(discussing policy of similar federal [*102] statute and allowing claim).
Accordingly we hold that Ledbetter did in fact have standing to challenge
the DOT's assessment of liquidated damages, and the court's ruling to the
contrary was error.
III
We now address the merits of
the claim that the damages withheld were unreasonable. Plaintiffs contend
that the liquidated damage provision was not intended to apply to the
period between substantial performance of the contract and final
acceptance, and that the provision is an invalid penalty clause on its
face and as applied. The DOT contends that the contract is incomplete
until accepted and that the damages withheld are therefore appropriate.
A.
The contract incorporated by
reference the Standard Specifications for Roads and Structures (1972) (SSRS)
issued by the N.C. Highway Commission, the predecessor to DOT. It provided
for liquidated damages as follows, SSRS § 108-11:
It is mutually recognized
that time is an [***11] essential element of the contract,
and that delay in completing the work will result in damages due to
public inconvenience, obstruction to traffic, interference with
business, and the increasing of engineering, inspection, and
administrative costs to the Commission. It is therefore agreed that
in view of the difficulty of making a precise determination of such
damages, a sum of money in the amount stipulated in the contract will be
charged against the Contractor for each calendar day that the work
remains uncompleted after the expiration of the completion date,
not as a penalty but as liquidated damages.
Should the Contractor or, in
case of default, the Surety fail to complete the work by the
completion date, a deduction of the amount stipulated in the
contract as liquidated damages will be made for each and every calendar
day that such contract remains uncompleted. This amount will be
deducted from any money due the Contractor or his Surety under the
contract, and the Contractor and his Surety will be liable for any
liquidated damages in excess of the amount due.
[*103] In case of default of
the contract and the completion of the work by the Commission, [***12]
the Contractor and his Surety will be liable for the liquidated damages
under the contract, but no liquidated damages will be chargeable for any
delay in the final completion of the work by the Commission due
to any action, negligence, omission, or delay of the Commission.
In any suit for the
collection of or involving the assessment of liquidated damages, the
reasonableness of the amount stipulated in the contract will be
presumed. The liquidated damages referred to herein are intended to be
and are cumulative, and will be in addition to [**766] every other
remedy now or hereafter enforceable at law, in equity, by statute, or
under the contract.
Permitting the Contractor to
continue and finish the work or any part thereof after the
expiration of the completion date shall in no way operate as a
waiver on the part of the Commission of any of its rights under this
contract. (Emphasis added.)
Since the terms
"completion of work" and "complete" are arguably
ambiguous, and since the DOT drafted the contract, plaintiffs contend that
any ambiguity should be construed against the DOT. See Wood-Hopkins
Contracting Co. v. State Ports Auth., 284 N.C. 732, [***13] 202
S.E. 2d 473 (1974). Therefore, they argue the contract requires only
substantial performance to preclude assessment of liquidated damages.
[HN4] This Court must construe
the contract as a whole and examine each provision in its proper relation
to the others. Sell v. Hotchkiss, 264 N.C. 185, 141 S.E. 2d 259 (1965).
Upon examination of the contract as a whole, and in light of the public
policy involved, we conclude that the contract is clear, that plaintiffs'
interpretation is incorrect and that liquidated damages are properly
assessable until the time the project is finally accepted. The damages
provision takes effect on failure "to complete the work by the
completion date." "Work" is defined in the contract as
including everything necessary to the "successful completion
of the project." SSRS § 101-75. (Emphasis added.) "Completion
date" is defined as the time by which the work is to be "satisfactorily
completed." SSRS § 101-16. (Emphasis added.) The contract contains
elaborate provisions governing inspection by the DOT. See [*104]
SSRS § 105-17. Under our law such [HN5] "satisfaction"
provisions clearly invest the inspecting party with discretionary power to
[***14] reject, subject only to restrictions of good faith. See Fulcher
v. Nelson, 273 N.C. 221, 159 S.E. 2d 519 (1968); see also
Mezzanotte v. Freeland, 20 N.C. App. 11, 200 S.E. 2d 410 (1973), cert.
denied, 284 N.C. 616, 201 S.E. 2d 689 (1974); 5 S. Williston, Law
of Contracts § § 675A-B (3d ed. 1961); 17A C.J.S. Contracts
§ § 494-95 (1963). It would clearly be inconsistent with such
discretionary power to interpret the contract so as to deny the DOT the
major contemplated means of assuring timely completion of the work in a
manner satisfactory to it. The record does not suggest that the DOT has
acted in bad faith in any way.
Moreover, the liquidated
damages provision itself expressly recognizes that failure to complete the
work would result in increased inspection and administrative costs to the
DOT. The damages contemplated therefore necessarily included the
inspection costs arising before final acceptance, even though
substantial performance might be complete. The damages provision itself,
with the definitions supplied elsewhere in the contract, thus clearly
indicates the intent to allow damages up to final acceptance.
Other relevant provisions
support this [***15] interpretation. The specialty specifications relating
to the sign work provide that no part of the project will be accepted
until the entire project is ready for final acceptance. The contract
specifically called for night inspections to check reflectivity. In the
general provisions, final inspection takes place upon "apparent
completion," and only if the construction "is found to be
satisfactorily completed" will the project be accepted. SSRS §
105-17. On default, the contractor is entitled to payment only for work
"satisfactorily completed." SSRS § 108-9(D). Contractors and
sureties remain obligated until completion and acceptance. SSRS §
§ 108-9(F); 108-14. Payment is not due until final acceptance. SSRS §
109-8 to -10.
Aside from their compensatory
function, liquidated damages provisions have long been held valid and
consistent with public policy as an appropriate means of inducing due
performance. See Robinson v. United States, 261 U.S. 486, 67 L.Ed. 760,
43 S.Ct. 420 (1923). It would frustrate this policy, and increase the
likelihood of inconvenience and danger to the public, to allow disputes
over substantial performance [**767] to affect such provisions. [***16]
The intent of [*105] the damages provision is clear and its application
proper. Plaintiffs do not contend that the DOT wrongfully delayed
acceptance or otherwise contributed to an excessive number of days for
which damages were assessed. As a matter both of contract interpretation
and of public policy, then, plaintiffs' interpretation of the contract
must fail.
B.
Plaintiffs contend that the
liquidated damages provision constitutes an unenforceable penalty, both on
its face and as applied. [HN6] A penalty is unenforceable under North
Carolina law. City of Kinston v. Suddreth, 266 N.C. 618, 146 S.E. 2d
660 (1966). A stipulated damages clause in a highway contract is not per
se a penalty, however. See L.A. Reynolds Co. v. State Highway
Comm'n, 271 N.C. 40, 155 S.E. 2d 473 (1967). Such provisions are
widely used in construction contracts and have been generally enforced as
an appropriate remedy for breach. See Annot., 12 A.L.R. 4th 891
(1982). The dispositive test was set forth by our Supreme Court:
Whether a stipulated sum
will be treated as a penalty or as liquidated damages may ordinarily be
determined by applying one or more aspects of the following [***17]
rule: '[A] stipulated sum is for liquidated damages only (1) where the
damages which the parties might reasonably anticipate are difficult to
ascertain because of their indefiniteness or uncertainty and (2) where
the amount stipulated is either a reasonable estimate of the damages
which would probably be caused by a breach or is reasonably
proportionate to the damages which have actually been caused by the
breach.'
Knutton v. Cofield, 273
N.C. 355, 361, 160 S.E. 2d 29, 34 (1968) (quoting 22 Am. Jur. 2d
Damages § 214 at 299 (1965)). The result of the application of this
test will also depend on the factual circumstances of each case. Id.;
Annot., 12 A.L.R. 4th 891, 900
(1982).
It is undisputed that the
damages that the parties might reasonably anticipate were difficult to
ascertain; in fact, the liquidated damages provision itself contains a
recitation to that effect. SSRS § 108-11. Plaintiffs attempt to avoid the
operation of this clause by arguing that the multiplicity of potential
breaches and the lack of any adjustment mechanism make the liquidated
[*106] damages provision invalid. However, the very multiplicity of
possible breaches in [***18] a large and complex project such as this is
what makes damages difficult to ascertain in the first place. Plaintiffs'
apparent contention that the DOT may only assess liquidated damages in
proportion to the relative value of the breach as against the value of the
contract as a whole overlooks this fundamental rationale for liquidated
damages provisions, and if implemented would serve only to foster
additional wasteful litigation. Moreover, the dollar amount of liquidated
damages is set by a separate stipulation not contained in the pre-printed
SSRS. There is no suggestion that this figure was arrived at by unfair
means, or that it does not represent part of the bargained-for contract.
We conclude that the first prong of the Knutton test has been
satisfied.
Accordingly, if either (1) the
amount stipulated was a reasonable estimate of damages or (2) it
was reasonably proportionate to the actual damages, the second prong of
the Knutton test was also satisfied. The DOT presented evidence
that the delay had caused it to incur $ 44,837.36 in additional costs.
This figure very closely approximates the $ 49,500.00 in liquidated
damages actually withheld. Plaintiffs argue [***19] that certain portions
of the alleged actual damages represented costs that would have been
incurred anyway, and that a breakdown by periods indicates that
overcharges of up to 90% resulted for certain months of the delay period.
No precise mathematical formula exists for determining what is
"reasonably proportionate;" the following language of our
Supreme Court is instructive:
[I]t is the general rule
that [HN7] the amount stipulated in a contract as liquidated [**768]
damages for a breach thereof, if regarded by the court as liquidated
damages and not as a penalty, may be recovered in the event of a breach even
though no actual damages are suffered. [Citations omitted.] Unless
the provision for liquidated damages be regarded as a penalty and
unenforceable, the effect of such clause in a contract 'is to substitute
the amount agreed upon as liquidated damages for the actual damages
resulting from breach of the contract, and thereby [prevent] a
controversy between the parties as to the amount of damages. . . . [T]he
sum stipulated forms, in [*107] general, the measure of damages in case
of a breach, and the recovery must be for that amount.'
Knutton [***20] v.
Cofield, 273 N.C. at 362-63, 160 S.E. 2d at 35-36 (quoting 22 Am.
Jur. 2d Damages § 235 at 321 (1965)) (emphasis added); see also
Restatement (Second) of Contracts § 356 comments a and b (1981);
Annot., 12 A.L.R. 4th 891, 936-48 (1982). These authorities
indicate that the disproportion must be such as to shock the judicial
conscience for a penalty to be found. In applying this test, the value of
the contract as a whole also bears on the question of proportion. Id.
In this case, even if we accept plaintiffs' arguments concerning actual
damages as true, they still amounted to at least 50% of the liquidated
damages assessed; the liquidated damages themselves amounted to only
approximately 1.5% of the total contract price. Accordingly, the second
prong of the Knutton test was satisfied, since the amount assessed
was reasonably proportionate to the actual damages incurred. We must
therefore further conclude that the trial court did not err in ruling that
the liquidated damages clause was valid as written and applied, and that
the DOT's assessment was entirely proper. Knutton v. Cofield.
IV.
In conclusion, although the
trial court ruled incorrectly on [***21] Ledbetter's standing to sue, that
error did not affect its order on the merits. The judgment appealed from
is therefore
Affirmed.