Many subcontractors operate at
the mercy of a general contractor and often find themselves delayed in
completing a project as a result of the general contractor's scheduling
changes. A recent decision from the North Carolina Court of Appeals
cautions subcontractors in this position to consult and carefully comply
with the terms of the contract between the general contractor and the
project owner in order to preserve their right to recover damages for
delays caused by another contractor.
The case of American
National Electric Corp. v. Poythress Commercial Contractors, Inc., 604
S.E. 2d 315 (2004) arose as a result of work performed by American
National Electric Corporation ("ANE") on the Cary Fire Station
No. 6 project. Poythress Commercial Contractors, Inc.
("Poythress") was the general contractor on the project and
executed a subcontract with ANE under which ANE would supply all material
and labor to perform certain electrical work for the project.
The subcontract provided for a
specific time period in which ANE would have to perform its electrical
work under the subcontract. During the course of ANE's work on the
project, Poythress made certain changes that directly affected the
schedule and sequence of ANE's electrical work. As a result, ANE was
denied sufficient access to perform all of its work on the project and
consequently was unable to complete the project in the time period
specified by the subcontract. Prior to ANE's completion of its work on the
project, its president gave verbal notice to the project superintendent
that ANE's work was being adversely impacted due to Poythress' schedule
and sequence changes. ANE, however, did not provide written notice of its
claim for damages until approximately five months later, after it had
completed its work on the project. ANE's claim for damages stated that
Poythress' changes to the scheduling and sequence of ANE's work caused
"labor inefficiencies and loss of productivity."
ANE filed a complaint against
Poythress and the project's architect seeking damages for breach of
contract. The trial court granted summary judgment in favor of Poythress
on the grounds that ANE failed to comply with the notice provisions of the
General Contract, which were incorporated into the subcontract.
The subcontract stated that
claims for "altered work, changes, modifications, change
conditions... and the damages resulting from ... shall be governed by the
provisions of the General Contract." The General Contract between
Poythress and the project's owner required that "claims for delay
compensation must be made in writing to the project's architect and owner
within 21 days after the occurrence or event giving rise to the claim or
within 21 days after the claimant first recognizes the condition giving
rise to the claim." ANE's president admitted that ANE was aware that
its work was being delayed in April 2000, but did not notify Poythress of
its delay claim in writing until September 2000, which was not within the
21 day period required by the General Contract.
The North Carolina Court of
Appeals found that ANE was bound to the contractor under the same
obligations as the contractor was bound to the owner. Those obligations
included the time in which the notice of delay for compensation had to be
provided. Therefore, the North Carolina Court of Appeals upheld the trial
court's decision in favor of Poythress because ANE failed to comply with
the notice provisions in the General Contract.
Given the court's decision in
this case, subcontractors faced with delays that will adversely impact
their compensation should consult the provisions in the General Contract
which may govern their obligations with the general contractor via a
"pass-through" or similar clause. Of course a timely claim made
by a subcontractor may give rise to a contractor's duty or ability to
raise the same claim with the project's owner, but an untimely notice by
the subcontractor may very well defeat the right to compensation
altogether for delays or other claims on the project.
If you have any questions
regarding this alert or other Construction Law related topics, please
contact Court Young at
704.342. or cyoung@poynerspruill.com
or Marshall Yoder at
704.342. pmyoder@poynerspruill.com.