|
On January 27, 2006, the North Carolina Supreme Court rendered a
decision in O & M Industries v. Smith Engineering Company (No. 502PA04)
which increases the Owner’s liability and obligation to pay Mechanic
Lien claims against funds asserted by Subcontractors and Suppliers.
The Supreme Court,
reversing the Court of Appeals, held that once an Owner receives a
Subcontractor’s Notice of Claim of Lien Upon Funds, it must withhold
monies from the Contractor in the full amount of the claim. Otherwise,
the Owner incurs personal liability directly to the lien claimant to the
extent of the wrongful payments made to the Contractor with no right to
set-off the additional costs for completion against the funds that
should have been withheld due to the lien.
This decision by the
Supreme Court runs contrary to the previously held assumption by many in
the construction industry that: (1) the Owner is only obligated to
withhold amounts “owed” the Contractor but that determination could only
be made after the Project was properly completed; and (2) if the
Contractor failed to properly complete the Project, the Owner could
setoff the cost of completion against the funds otherwise subject to the
lien.
The underlying facts
of O&M Industries were that the Owner of a manufacturing facility
contracted with a Contractor for improvements to its plant. The
Contractor subcontracted with the Plaintiff to furnish certain equipment
to the Project. The Subcontractor delivered the equipment but at about
the same time, served the Owner with a Notice of Claim of Lien Upon
Funds in the amount of $100,000.00. After the Owner received the
Notice, it made two payments to the Contractor each in the amount of
$150,000.00. The Contractor was apparently having financial difficulty
and the Owner made the payments in an effort to keep the Contractor
working on the Project. As you might expect, the Contractor later filed
bankruptcy and failed to complete the Project.
The Subcontractor
then filed suit against the Owner claiming it was entitled to recover on
its Claim Upon Funds. The Owner denied the Sub was entitled to any
recovery since its cost of completion exceeded any amount owed the
Contractor. Nevertheless, the Supreme Court held that under our
Mechanic’s Lien Statute (N.C.G.S. §44A-18 and 44A-20), once the Owner
received the Notice, it had a duty to retain funds in the total amount
of the lien. Since the Owner made subsequent payments to the
Contractor, it was considered an admission by the Owner that amounts
were owed. Therefore, the Owner became personally liable for the amount
of payments made to the Contractor up to the amount of the Plaintiff’s
Claim Upon Funds.
If an Owner properly
withholds the amount of the Claim Upon Funds, it can use any remaining
contract balance to complete the project. However, it is not clear from
the Court’s opinion whether an Owner can set-off against the
withheld funds subject to the lien if the remaining funds are not
sufficient for the Owner to complete the Contractor’s work.
In the Court’s
opinion, it was proper to place this additional risk on the Owner
because once a lien is served, the Owner has notice of a problem and can
avoid or rectify the problem because it has control of the funds.
However an Owner’s exercise of that control may result in substantial
delays to a Project and an increase in completion costs. Many
Contractors may deny owing any amount to a claimant or, being unable or
unwilling allow a disruption of its cash flow, and refuse to complete
the work unless paid.
Under our Mechanic’s
Lien Statute, a Subcontractor may assert a Claim of Lien Upon Funds
“whether or not such amounts are due and whether or not performance or
delivery is complete“ (44A-18(f)). In other words, a Lien Upon Funds
may be asserted by a Subcontractor in the full amount of its contract
not yet due for payment from the Contractor, but under the court’s
rationale, the entire amount should be withheld from the Contractor. In
such event, the likelihood of a Contractor being unable to complete a
project will substantially increase.
Conclusion
What is an Owner to
do in order to avoid personal liability due to a Claim Upon Funds on a
construction project?
First, an Owner
should make sure its contract with the General Contractor includes
provisions that require the Contractor to “bond off” any liens and
indemnify the Owner against any costs or expenses, including attorney
fees, incurred in connection therewith.
Second, Owners could
require the Contractor to provide performance and payment bonds,
although the cost of the premiums will increase the cost of the project
by about one percent (1%). (Remember that on private construction
projects, a Subcontractor may assert both a lien claim as well as claim
against the payment bond.
Third, (or in the
alternative), an Owner should promptly withhold funds from the
Contractor up to the amount of the Claim and demand that the Contractor
resolve or ‘bond-off’ the lien. Thanks to a recent amendment of our
Mechanic’s Lien Statute there is now a provision which allows the
bonding off of a Claim Upon Funds. Otherwise an Owner will become
personally liable for the amount owed to a subcontractor and may be
“paying twice” for the same work.
If you have any
questions regarding this alert or other Construction Law issues, please
contact John Shaw at
919.783.2809 or
jshaw@poynerspruill.com. |